| The Toon Studio expansion project was first confirmed in January 2005, followed by the confirmation of Cars Race Rally as its second new attraction in the months which followed. Construction didn’t begin until early 2006, however, but rapid progress was soon made. This page aims to chart the key construction milestones of this brand new Imagineering project… Pre-Construction   2002 to Early 2006 The corner plot of Animation Courtyard sits empty. February 2006  10th February 2006 Land is cleared and prepared. The Mickey’s Trailer character location is moved to Production Courtyard. June 2006  10th June 2006 Exactly 1 year to go until grand opening. Construction fences move outwards to cover the full area of the new Toon Studio attractions and the Flying Carpets planting enhancements. August 2006  19th August 2006 Foundations are dug for the two pairs of turntables and temporarily lined with tarpaulin for protection before concrete is laid. Existing surrounding tarmac on the Animation Courtyard side is trimmed back to its new dimensions and curved style. September 2006   9th September 2006 The lower sections of the turntable foundations are poured and cast in concrete, whilst new curbs are added to the bordering path opposite Animagique and the first sandy grey flooring is poured around the front of the ride plateau. At the far end of the construction site, the first concrete walls are cast for the Radiator Springs-themed queue building. October 2006  5th October 2006 The queue building races ahead, with the circular entrance section taking shape and the bare fa�ades of the three storefronts cast and constructed in concrete.  15th October 2006 The concrete foundations and plateau for the ride system and turntables is completed, with the edges showing where the ride platforms will sit in place. Land around the area is dug out to provide the miniaturized movie set “canyon” effect of the 1 metre height difference.  16th October 2006 The concrete form of the queue building progresses further, whilst land is prepared for the outdoor “backstage” sections and the slope down towards the ride area. The first steel structure appears for the canopy and Flo’s V8 Caf� section.  21st October 2006 As diagonal steel supports for the roof of Flo’s V8 Caf� appear, a breeze block wall wraps around the ride area to provide a retaining wall for landscaping and the core foundations and support for the rocky desert themeing to come. November 2006  1st November 2006 A steel roof structure is now in place at Flo’s V8 Caf�.    4th November 2006 Work continues on the ride foundations, including those for the automatic safety gates and operating system, whilst the brick wall is prepared for its upcoming themeing. Studio Tram Tour gives a closer look at the queue buildings under construction, whilst the short Autumn days show Toon Studio under nightfall.   7th November 2006 Before the addition of more trees and movement of the fences, Flying Carpets Over Agrabah gives a clear view across to both the ride platform and the Radiator Springs queue building. The entrance is the largest opening, higher than the ground around it to allow for the final layer of coloured flooring to be poured. December 2006    30th December 2006 Window frames and more features are added to the queue building, red ochre rockwork surrounds the ride area, more foundations for the boarding area and ride platform are prepared, the Willy’s Butte rock formation is completed and the first bushy conifer trees are added! February 2007    3rd February 2007 More details appear on the Radiator Springs storefronts, such as the tires of Casa Della Tires, whilst scaffolding surrounds the V8 Caf� canopy and Willy’s Butte rock. The main control booth has been added and preparations are underway to install the ride system itself.   20th February 2007 All 12 of the Cars vehicles are installed along with their turntable platforms. After several days of fitting, they are covered with protective plastic tarps. More details have been added to the brown pillars of Flo’s V8 Caf�, which has now gained a bright turquoise roof. Extra plants, such as the well-established tree in the first photo, have also been added. March 2007     5th March 2007 Installation work continues on the ride area as a collection of large wooden poles appear, surrounding the canyon area. A look over the construction wall reveals the installed control booth and the outdoor queue/boarding area (after the initial two corridors inside the buildings themselves), which has now received a metal roof and gutters, paths and queue barriers. The circular entrance building has also been decorated with its first magnolia tiles. For more construction photos and all the latest updates, see the Photos Magiques Construction Gallery. |